Background
"AIR 6000 will deliver a New Air Combat Capability (NACC) comprising around 100 Conventional Take Off & Landing (CTOL) F-35A Joint Strike Fighters (JSF) and all necessary support, infrastructure and integration to form four operational squadrons and a training squadron.
Australia joined the System Development and Demonstration phase of the JSF Program in October 2002 and through AIR 6000 Phase 1B (approved), undertook a program of detailed definition and analysis activities leading up to Government Second Pass
(acquisition) approval for Phase 2A/2B Stage 1, in November 2009.
Phase 2A/2B will acquire no fewer than 72 F-35A to form three operational squadrons and a training squadron, with first deliveries in 2014. Stage 1 (approved) will acquire 14 F-35A and associated support and enabling elements necessary to establish the initial training capability in the US and to allow conduct of Operational Test in the US and Australia. Stage 2 (unapproved) plans to acquire the remaining (at least) 58 F-35A and support and enabling elements, bringing the total to 72 aircraft. Stage 2 is planned for approval in 2014-15.
Australia’s first JSF will remain in the US for a number of years for initial conversion training of Australian pilots and maintainers, and also participation in operational test activities. Australia’s initial JSF are planned to commence arriving in Australia in 2018. They will commence dedicated Australian operational test activities, primarily to ensure effective integration with other ADF air and ground systems.
Phase 2C (unapproved) is the planned acquisition of a fourth operational JSF squadron to bring the total number of aircraft to around 100. The decision to acquire the fourth operational JSF squadron will be considered in conjunction with a decision on the withdrawal of the Super Hornet. A decision on this final batch of JSF is not expected before 2015....
...AIR 6000 Phase 2A/2B New Air Combat Capability – 3 squadrons
Scope
AIR 6000 Phase 2A/2B is the first acquisition phase for the New Air Combat Capability (NACC) project and will comprise three operational squadrons, a training squadron, associated support and enabling capabilities. Initially the JSF will be complemented by a squadron of F/A-18F Super Hornets, and together they will fulfil the functions of air dominance and strike provided by Air Force’s F/A-18A/B aircraft....
...AIR 6000 Phase 2C New Air Combat Capability – 4th squadron
Scope
AIR 6000 Phase 2C is the final acquisition phase for the AIR 6000 project and will comprise a fourth operational squadron of F-35A aircraft, associated support and enabling capabilities, and attrition aircraft to support the planned fleet life. The decision to acquire the fourth operational JSF squadron will be considered in conjunction with a decision on the withdrawal of the F/A-18F Super Hornet in the FY 2015-16 to FY 2017-18 timeframe...."