Some F-35 suppliers are having trouble delivering parts on schedule, and Turkey’s departure could make that worse
12 May 2020 Valerie Insinna [Complicated BEST READ at URL]
"WASHINGTON — Lockheed Martin’s F-35 Joint Strike Fighter is on the verge of full-rate production, with a decision slated for early 2021. But a congressional watchdog group is concerned that as the company ramps up F-35 production, its suppliers are falling behind. And those supply chain problems could get even worse as Turkish defense manufacturers are pushed out of the program, the Government Accountability Office said in a May 12 report.
According to the GAO, the number of F-35 parts delivered late skyrocketed from less than 2,000 in August 2017 to upward of 10,000 in July 2019. The number of parts shortages per month also climbed from 875 in July 2018 to more than 8,000 in July 2019. More than 60 percent of that sum was concentrated among 20 suppliers, it said.
“To mitigate late deliveries and parts shortages — and deliver more aircraft on time — the airframe contractor has utilized methods such as reconfiguring the assembly line and moving planned work between different stations along the assembly line,” the GAO said.
“According to the program office, such steps can cause production to be less efficient, which, in turn, can increase the number of labor hours necessary to build each aircraft,” which then drives up cost, the GAO added....
...Hard times for the F-35’s engine supplier
Not all F-35 production trends reported by the GAO were bad for the aircraft. Since 2016, Lockheed has made progress in delivering a greater proportion of F-35s on schedule, with 117 of 134 F-35s delivered on time in 2019.
However, one of the biggest subsystems of the F-35 — the F135 engine produced by Pratt & Whitney — drifted in the opposite direction, with a whopping 91 percent of engines delivered behind schedule. At one point in 2019, Pratt & Whitney stopped deliveries of the F135 for an unspecified period due to test failures, which also contributed to the reduction of on-time deliveries.
According to the Defense Contracts Management Agency, “there have been 18 engine test failures in 2019, which is eight more than in 2018, each requiring disassembly and rework,” the GAO wrote. “To address this issue, the engine contractor has developed new tooling for the assembly line and has established a team to identify characteristics leading to the test failures. Plans are also in place for additional training for employees.”"
Source: https://www.defensenews.com/air/2020/05 ... hat-worse/