Lockheed Martin conducts engine fit checks on first F-35 JSF
February 10, 2006 (by
Jeff Hollenbeck) -
While waiting on the delivery of a wiring harness necessary for full integration of the Pratt & Whitney F-135 engine, Lockheed Martin conducted a successful engine fit check on the floor of its Ft. Worth, TX assembly plant earlier this month.
Pratt & Whitney completed assembly of the F-135 engine in December of 2005. Ground tests of the F-35 are scheduled to begin in Spring of 2006 with the first flight to follow in the Fall.