F-16 Reference
5th Gen Fighters
|
| Author |
Message |
|
neptune
|
Posted: Jul 22, 2010 - 11:40 PM
|
|
|
Forum Veteran

Joined: Oct 24, 2008 - 01:03 AM
Posts: 632
Location: 77007
Status: Offline
|
|
energo wrote:
F-35 flight summary - passing 300 sorties
2010 year to date, as of July 20:
AF-1 - 30
AF-2 - 34
AF-3 - 4
BF-1 - 25
BF-2 - 15
BF-3 - 27
BF-4 - 17
CF-1 - 14
Total - 166 of 144 planned
Test points - 1604 of 1405 planned
Program overall flights - 303
See also F-35 testing ahead of schedule
B. Bolsøy
Oslo
Quietly working away at completing the 2010 goals and schedules. Awesome! What a great time the pilots, engineers and maintainers are having. I'm envious of the challenges and opportunities. Best Wishes and thanks Energo! |
|
|
|
|
|
 |
|
Sponsor
|
Posted: Feb 12, 2012 - 5:45 AM
|
|
|
F-16.net Sponsor
|
|
|
|
 |
|
VarkVet
|
Posted: Jul 23, 2010 - 08:05 AM
|
|
|
Elite 1K

Joined: Oct 30, 2006 - 04:31 AM
Posts: 1397
Status: Offline
|
|
neptune wrote:
Quietly working away at completing the 2010 goals and schedules. Awesome!  What a great time the pilots, engineers and maintainers are having. I'm envious of the challenges and opportunities.  Best Wishes and thanks Energo!
Oh stop it ... GOT GUN?
http://www.youtube.com/watch?v=OXg6J9upaCg |
_________________ My eyes have seen the glory of the Lord and the esthetics of the Flightline
|
|
|
|
 |
|
VarkVet
|
Posted: Jul 23, 2010 - 08:28 AM
|
|
|
Elite 1K

Joined: Oct 30, 2006 - 04:31 AM
Posts: 1397
Status: Offline
|
|
|
|
 |
|
VarkVet
|
Posted: Jul 24, 2010 - 03:12 AM
|
|
|
Elite 1K

Joined: Oct 30, 2006 - 04:31 AM
Posts: 1397
Status: Offline
|
AF-3 got number 5 in today ... was trying for 6 then weather came in.
 |
_________________ My eyes have seen the glory of the Lord and the esthetics of the Flightline
|
|
|
|
 |
|
spazsinbad
|
Posted: Jul 28, 2010 - 04:39 AM
|
|
|
Elite 3K

Joined: May 05, 2009 - 10:31 PM
Posts: 3931
Location: OZ
|
STOVL F-35 not flying so often July 27, 2010 - Bob Cox
http://startelegram.typepad.com/sky_tal ... often.html
"Give Lockheed Martin CEO Bob Stevens some props for telling the truth, warts and all. Stevens, in the midst of reassuring Wall Street investment analyst Monday that all is well with the the F-35 program, dropped one morsel that was known to some degree, but not in detail.
Flight testing of the F-35B STOVL model intended for the Marines is lagging behind schedule at the Navy's Patuxent River flight test center.
At the end of June, Stevens said, only 74 of 95 test flights planned for the first six months had been conducted. Lockheed spokesman John Kent updated that information after the call, saying 91 flights had been completed as of Tuesday. The goal is to have completed 125 F-35B flights by the end of July.
Stevens said the component “failure rates are higher than predicted” and that Lockheed and the military test managers are working to understand why failures are occurring and how to improve their design and manufacture. Failing components are cooling fans that hold down fuel temperatures, lift fan doors actuators and other switches. Stevens said there have been no failures of key components of the STOVL propulsion systems, the engine or the lift fan system.
The lagging pace of test flights puts more pressure on a program already in the spotlight and facing an aggressive flight testing pace over the next few years to begin to compensate for the already years-long delays in development and soaring cost estimates.
By contrast, testing of the two other models is going well. The two F-35A aircraft being flown at Edwards Air Force Base in California and the one F-35C model, being flown at Fort Worth still, are both completing flights well ahead of plan."
http://startelegram.typepad.com/.a/6a00 ... f85970c-pi (large photo F-35B stol/hover mode) |
_________________ http://www.adf-history.com/adf/?cat=7 http://alturl.com/4a4ko http://www.youtube.com/user/bengello/videos
|
|
|
|
 |
|
neptune
|
Posted: Jul 29, 2010 - 03:08 AM
|
|
|
Forum Veteran

Joined: Oct 24, 2008 - 01:03 AM
Posts: 632
Location: 77007
Status: Offline
|
RT @amanda__maureen: JUST SAW THE 3RD EVER F-35 VERTICAL LANDING!, http://www.flightglobal.com/blogs/the-dewline/
ARES Blog; Graham Warwick wrote: BF-1, the first F-35B and the one having the most problems, is the only aircraft instrumented and cleared for STOVL flight testing. It has to perform about 50 vertical landings to clear the rest of the fleet to begin STOVL ops. Fleet clearance is needed by year-end for at-sea testing to begin in March 2011. So the pressure is on.,
http://www.aviationweek.com/aw/blogs/de ... 329aef79a7  |
|
|
|
|
|
 |
|
neptune
|
Posted: Aug 05, 2010 - 07:57 PM
|
|
|
Forum Veteran

Joined: Oct 24, 2008 - 01:03 AM
Posts: 632
Location: 77007
Status: Offline
|
|
VarkVet wrote:
AF-3 got number 5 in today ... was trying for 6 then weather came in.
Graham Warwick @ Aviation Week
Lockheed Martin has launched an investigation into parts failures that have slowed flight testing of the STOVL F-35B, but the simpler CTOL F-35A continues to rack up flights. Overall the program logged 49 flights in July, against 41 planned, for a year-to-date total of 185 against 159 planned (target for the year being 394).
But the four F-35Bs at Pax River logged only 22 of those flights, eight short of the plan for the month, and the STOVL fleet ended July with a year-to-date total of 96 flights against 124 planned. August has started well, however, with four STOVL flights so far - and, more importantly, four vertical landings in the past week.
Lockheed says the F-35B reliability and flight rate is improving, but it will surely be a challenge to clear the fleet for STOVL operations by year end to pave the way for initial ship operations in March 2011. Testing has been slowed by maintenance issues with cooling fans, lift-fan door actuators, valves and power system components.
The two F-35As and sole F-35C now flying have been much more reliable by comparison. To address the parts failures on the STOVL aircraft, Lockheed says it has "implemented a series of improvement actions with our suppliers, including root-cause and corrective-action processes, executive-level reviews and potential withholding of performance fees."
http://www.aviationweek.com/aw/blogs/defense/ |
|
|
|
|
|
 |
|
neptune
|
Posted: Aug 24, 2010 - 03:53 PM
|
|
|
Forum Veteran

Joined: Oct 24, 2008 - 01:03 AM
Posts: 632
Location: 77007
Status: Offline
|
JSF Jocks
Posted by Guy Norris at 8/20/2010 12:50 PM CDT
U.S. Air Force test pilot Lt. Col. Hank "Hog" Griffiths believes he may have flown faster in an F-35 Joint Strike Fighter than anyone else.
Griffith says in June he took the F-35A to 583 KCAS (exceeding Mach 1.2). “I may be the first to fly this fast in the jet so far,” he muses. “The jet handles well, and she just wants to fly fast. It has a monster engine. It looks like an aircraft that’s built around an engine.”
Griffiths, who is also 461st Flight Test Squadron Commander and F-35 Integrated Test Force (ITF) director at Edwards AFB, was the pilot of one of the two F-35As flown to the desert base in May for the start of developmental test and evaluation (DT&E). Griffith was accompanied by Lockheed Martin F-35 Chief Test Pilot Jon Beesley who flew the jets, known as AF-1 and AF-2, nonstop in the first multi-ship, long-range F-35 flight.
Not surprisingly, Griffith is clearly a huge fan of the CTOL version which he says is racking up test points three times faster than scheduled. By the time of my visit earlier this week, the two F-35As had completed 53 sorties and 536 unique test points. The plan called for the pair to have completed 17 sorties and 150 test points by now, meaning that progress is being achieved at roughly three times the expected rate.
But can this be sustained? Griffith believes the answer is yes, but cautions that the more complex testing of the radar and electronic warfare configured aircraft next year could pose more challenges to the rate. Lockheed Martin’s target for the overall ITF test rate is 12 flights per month per aircraft. “That’s really three times per week, but already with the reliability of AF-1 and AF-2 we can schedule a flight every day,” he says.
AF-1 and 2 are focused on flight sciences objectives, including envelope expansion, loads testing, flutter clearance and flying qualities. “Our objective by the end of 2010 is to clear the envelope to 40,000-ft, subsonic with 80% of the potential design limit load,” Griffith says. In June, initial supersonic testing for loads and flutter was completed to around Mach 1.2/580 KCAS and 39,000-ft. Air refueling clearance tests at 15,000-ft are also getting underway, work having already cleared the refueling envelope at 20,000-ft and 30,000-ft.
Even when loaded internally with two 2,000lb GBU-31 Joint Direct Attack Munitions and two AIM-120 AMRAAMs, Griffith says the sheer power of the Pratt & Whitney F135 is evident. “The engine has a lot of thrust. It’s been fun to outrun the F-16 (chase aircraft). They can’t keep up. If we go to full military power the F-16 has to go to afterburner to keep up.”
The current flight tests with weapons are for captive carriage purposes only, as actual weapons tests will come in later phases of the program next year following the arrival (later this year) of AF-3 and AF-4 – the first to come configured with block 0.5 missions systems software. In the meantime Griffith says captive carry tests of AIM-9X Sidewinder air-to-air missiles are likely before long. The overall task of the initial test fleet at Edwards includes development, test and evaluation of propulsion, aerial refueling, logistical support, weapons integration and flight-envelope expansion.
http://www.aviationweek.com/aw/blogs/de ... d=blogDest
"..racking up test points three times faster than scheduled. ,,, the two F-35As had completed 53 sorties and 536 unique test points...vs. The plan to have completed 17 sorties and 150 test points"
Curious, how is the "Sea" Lightning doing?.. and when is it expected to move to PAX?
"B" Lightning? flying or "Hanger Queen"??  |
|
|
|
|
|
 |
|
thg
|
Posted: Aug 24, 2010 - 04:23 PM
|
|
|
Banned
Joined: Jul 24, 2010 - 11:27 PM
Posts: 49
Location: Maryland
Status: Offline
|
F-22 Lessons Drive Faster F-35 Testing
http://www.aviationweek.com/aw/generic/ ... annel=awst
Quote:
Flight-testing of the F-35 Joint Strike Fighter here is running almost three times faster than expected, forcing program officials to accelerate follow-on support testing to keep pace.
At the same time, program officials also confirm plans to add extra resources to the flight tests here, just as they are at the U.S. Navy’s test center at NAS Patuxent River, Md., to ensure the program stays on a revised schedule that extends development by 13 months.
Since ferrying from Lockheed Martin’s Fort Worth facility on May 17, the two initial conventional-takeoff-and-landing (CTOL) F-35As have completed 53 sorties, 36 beyond the 17 they were slated to have finished by now. “We’ve also executed 536 unique test points out of a planned 150,” says Lt. Col. Hank Griffith, commander of the 461st Flight Test Sqdn. and director of the F-35 Integrated Test Force (ITF).
Maj. Gen. David Eichhorn, commander of the Air Force Flight Test Center here, says the F-35A is “exceeding expectations at this point in the program” and that the accelerated test rate is linked directly to aircraft performance and availability. “We want to run as fast as the aircraft will let us,” he says. As a result, tests of inlet rigs and weapons bay door opening at Lockheed Martin will be conducted sooner than originally planned. “Now they are having to move that analysis forward. So maybe it is possible we could continue and finish early,” Griffith says.
“It’s a testament to the health and reliability of the CTOL aircraft as well as the experienced people here in the test team,” says Griffith, who notes that lessons from the F-22 test program are paying dividends. As well as recruiting people to work on the F-35 directly from the F-22, Griffith says early planning between the ITF and Lockheed Martin helped avoid the extended preflight-test delays experienced early on in the F-22 program.
“With the F-22, we didn’t start the flight test for a long time because they basically had to finish building it. So with the F-35, we worked very closely with Lockheed Martin to understand the traveled work,” Griffith says, referring to items that may have had to be completed here. As it turned out, the initial pair of aircraft arrived “squawk-free” and test-ready. “We flew the first test mission two days after we arrived and in the first two weeks we did nine sorties,” he adds. In addition, maintenance and support personnel from here traveled to Patuxent River to gain experience on the F-35 before delivery.
However, tempering the exuberance of this initial “honeymoon” phase, Eichhorn is also pragmatic. “I’m cautiously optimistic, but you never know what’s around the next corner in flight test. Once you get into the missions systems, it’s a different side of flying.” There are “things that need to be tweaked, and things that need to be changed, and we’re working that as a team with Lockheed Martin and the government,” he says.
“The F-35 is a typical test program and we’re running into the typical things you’d run into. What we don’t know yet is the cumulative effect of those things,” Eichhorn says. Griffith describes the issues as “normal program hiccups,” but says the overall performance of the aircraft has been solid, with sustained test sorties. Although the integrated power pack (IPP) is mentioned as the cause of a “few issues,” Griffith says that even these “have not really impacted us at all.” The IPP combines the auxiliary and emergency power units and environmental control system to save weight, and it is required to start the engine and power the aircraft.
Thermal management, another potential concern for the F-35 test team, has not been an issue. “We’ve been operating the jet out in the sun for three hours and never overheated,” says Griffith, noting that chilled fuel has been available but not used. However, the litmus test of the power and thermal management system, of which the IPP is a subsystem, will come during upcoming tests of the first fully equipped systems aircraft, AF-3. Cooling requirements will be more acute on it because it will be configured with Block 0.5 mission system software, airborne radar and electronic warfare systems.
AF-3 is undergoing anechoic tests at Lockheed Martin and is expected to ferry here in October. Although the initial systems tests will begin in the relatively cooler winter weather here, the higher temperatures in the spring and summer of 2011 will be the true test, Griffith says. “Come and ask me the same question this time next year,” he says. AF-4, the second systems aircraft, will arrive by year-end, but will have its radar removed for weight and balance reasons before being used for high angle-of-attack testing.
The F-35s were delivered here to undertake developmental test and evaluation (DT&E) for propulsion, aerial refueling, logistical support, weapons integration and flight-envelope expansion. They form part of an extended ITF that also includes the Navy’s test center, where four short-takeoff-and-vertical-landing (Stovl) F-35Bs are based, as well as Lockheed Martin’s Fort Worth site.
The first two aircraft, AF-1 and -2, are focused on flight sciences objectives, including envelope expansion, loads testing, flutter clearance and flying qualities. “Our objective by the end of 2010 is to clear the envelope to 40,000 ft. subsonic with 80% of the potential design limit load,” Griffith says. In June, initial supersonic testing for loads and flutter was completed to Mach 1.2/580 KCAS and 39,000 ft. Air refueling clearance tests at 15,000 ft. are also getting underway. The refueling envelope has already been cleared at 20,000 and 30,000 ft.
The ITF here will eventually include eight F-35As, two more than initially planned under the revised resource allocation. The two extra low-rate initial production aircraft will join the program in 2011. Recruiting is also underway to staff additional operational test positions. “We’re trying to get about a year ahead to keep up with the pace of the test program,” says Eichhorn.More people will be added to support the growing numbers of chase aircraft and tanker aircraft. Lockheed Martin will lead an industry team effort to add 112 maintenance and test operations employees. The total is expected to grow to 740, including industry and government personnel, says Griffith.
Planning for the establishment of the JSF Operational Test Team (JOTT) here from 2012 also continues, with signs of a strengthened bond between the developmental and operational test teams. “We’ve grown closer together. The JOTT team is already integrated with test planning and the weapons scenarios we will use in DT&E,” says Griffith. The unit will include 20 CTOL, carrier and Stovl variants, two of which will be U.K. aircraft. Eichhorn says that despite the increasing indications of harmony, the “integrated developmental and operational testing is still a work in progress.”
|
|
|
|
|
|
 |
|
spazsinbad
|
Posted: Sep 02, 2010 - 12:29 AM
|
|
|
Elite 3K

Joined: May 05, 2009 - 10:31 PM
Posts: 3931
Location: OZ
|
F-35B delays lead to re-phased flight test schedule By Stephen Trimble DATE:01/09/10 SOURCE:Flight International
http://www.flightglobal.com/articles/20 ... edule.html
The F-35 programme will likely reshuffle the flight test schedule again as Lockheed Martin continues to struggle with the reliability of the short-takeoff-and-vertical-landing variant (STOVL).
It is not immediately clear if the possible "rephasing" of the flight test schedule would result in a new overall delay for any of the three F-35 variants. Addressing a group of market analysts on 1 September, Lockheed Martin CEO Robert Stevens says a recent push to improve the reliability of the F-35B STOVL variant has fallen short of expectations.
As a result, an ongoing technical baseline review commissioned by the F-35 joint programme office is focusing on the viability of a dramatically reduced flight test schedule adopted earlier this year.
"I'm quite sure we're going to see a re-phasing of the STOVL flight test programme to recognise actual performance to date," Stevens says.
The previous schedule called for Lockheed to complete more than 1,200 flight tests by all three variants in Fiscal 2010. Earlier this year, government officials relaxed that number significantly , dropping the overall number to 394 flight tests in FY2010 and about 1,000 in FY2011.
But the STOVL version has failed to keep pace with the government's reduced expectations.
Stevens says that a series of reliability improvements has delivered positive results for the flight test programme, but not enough to overcome the increasing delays.
"We're catching up but not at the rate at which we had [predicted] in the initial plan," Stevens says.
The results of the technical baseline review will be finalised by November, Stevens says.
Re-phasing the flight tests will allow Lockheed to "move resources and talent in place to improve the flow of reliable parts and recover flight tests and test points", he says.
By the end of July, Lockheed's four STOVL flight test aircraft had completed 74 out of 95 scheduled flights.
Stevens had attributed to the flight test delays to poor reliability on key components, such as thermal cooling fans, door actuators and power system switches.
The F-35B's reliability problems do not require "fundamental engineering" changes and the aircraft "has a good flying character", Stevens says." |
_________________ http://www.adf-history.com/adf/?cat=7 http://alturl.com/4a4ko http://www.youtube.com/user/bengello/videos
|
|
|
|
 |
|
neptune
|
Posted: Sep 02, 2010 - 05:59 AM
|
|
|
Forum Veteran

Joined: Oct 24, 2008 - 01:03 AM
Posts: 632
Location: 77007
Status: Offline
|
|
|
|
 |
|
energo
|
Posted: Sep 08, 2010 - 02:15 AM
|
|
|
F-16.net Moderator

Joined: Dec 09, 2007 - 02:06 PM
Posts: 439
Status: Offline
|
Flight test update
August summary:
F-35A: 22 of 9 planned
F-35B: 26 of 28 planned
F-35C: 0 of 0 planned (CF-1 in final finishes, heading to NAS PAX ca. October)
As of Sept. 3:
Year to date flights (CY 2010): 239 to 202 planned
Year to date test points: 2410 to 1943 planned
Total flights: 376
B. Bolsøy
Oslo |
Last edited by energo on Sep 08, 2010 - 02:22 AM; edited 1 time in total
|
|
|
|
 |
|
SpudmanWP
|
Posted: Sep 08, 2010 - 02:22 AM
|
|
|
Elite 2K

Joined: Oct 12, 2006 - 08:18 PM
Posts: 2891
Location: California
Status: Offline
|
Is the F-35A number in error? Only 9 flights planned?
If the F-35B is only 2 flights (for August) behind due to the parts problems, that is not too shabby. |
_________________ "The early bird gets the worm but the second mouse gets the cheese."
|
|
|
|
 |
|
energo
|
Posted: Sep 08, 2010 - 02:25 AM
|
|
|
F-16.net Moderator

Joined: Dec 09, 2007 - 02:06 PM
Posts: 439
Status: Offline
|
|
SpudmanWP wrote:
Is the F-35A number in error? Only 9 flights planned?
If the F-35B is only 2 flights (for August) behind due to the parts problems, that is not too shabby.
Spud,
F-35A flights are verified; 22 of 9 planned in August.
F-35B catching up, though still a bit behind schedule: 26 of 28 planned.
B. Bolsøy |
|
|
|
|
|
 |
|
SpudmanWP
|
Posted: Sep 08, 2010 - 04:21 AM
|
|
|
Elite 2K

Joined: Oct 12, 2006 - 08:18 PM
Posts: 2891
Location: California
Status: Offline
|
Thanks for the confirmation.
I wonder why they only had 9 F-35A flights planned. |
_________________ "The early bird gets the worm but the second mouse gets the cheese."
|
|
|
|
 |
|
|
|
|