fang
PostPosted: Apr 03, 2012 - 07:01 AM Reply with quote Back to top
Active Member
Active Member


Joined: Oct 28, 2006 - 11:07 AM
Posts: 144

Status: Offline
maus92 wrote:
The USAF FY 2013 PB Production Schedule has 3 jets delivered (1-A, 2-B) in April, 3 jets (1-A, 2-B) in May, 2 jets (1-A, 1-B) in June, 3 jets (1-A, 2-B) in July - which is the balance of LRIP-III (FY2009) jets. For the rest of FY12, there are 3 jets (1-A, 2-B) in August, 3 jets (1-A, 1-B, 1-C) in September - all LRIP-IV (FY2010) jets. October (beginning of FY2013) continues LRIP-IV with 4 jets (2-A, 1-B, 1-C), in November, 2 jets (1-A, 1-B), and December, 5 jets (1-A, 3-B, 1-C).

From CY2013 - CY2017, there are generally 2-4 jets delivered per month, with a few exceptions. Starting in CY2018, the rate increases to 5-6 jets per month.

Thank you for sharing, seems like there is more time than planes.
I wonder if by this production rate and the small orders they will deliver the next LRIP's jets sooner...
 View user's profile Send private message  
 
Sponsor
New postPosted: May 20, 2013 - 10:37 PM Back to top
F-16.net Sponsor





  Send private message  
 
sufaviper
PostPosted: Apr 03, 2012 - 03:30 PM Reply with quote Back to top
Active Member
Active Member


Joined: Nov 01, 2011 - 04:30 PM
Posts: 131

Status: Offline
fang-

My understanding is that the line is currently equipped and manned to produce ~45 jets a year (I think I remember that the purchase of the equipment and hiring/training of personnel started before the LRIP orders were curtailed). So that would lead me to believe that yes, the next few LRIP's that only have ~30 planes in them will be produced ahead of schedule.

Sufa Viper
 View user's profile Send private message  
 
marksengineer
PostPosted: Apr 04, 2012 - 05:40 PM Reply with quote Back to top
Active Member
Active Member


Joined: Jul 18, 2011 - 10:01 PM
Posts: 192
Location: Ohio
Status: Offline
Looking at the numbers it appears that in CY 2014 L-M will have less F-35's to build than it has capacity. My calculation is 38 to build for the mentioned capacity of 45 assuming it takes one year between contract signing and start of production. So what happens?
 View user's profile Send private message Visit poster's website  
 
SpudmanWP
PostPosted: Apr 04, 2012 - 05:45 PM Reply with quote Back to top
Elite 3K
Elite 3K


Joined: Oct 12, 2006 - 08:18 PM
Posts: 4266
Location: California
Status: Offline
In CY14 they are building Partner and FMS jets that do not appear on the schedule.

_________________
"The early bird gets the worm but the second mouse gets the cheese."
 View user's profile Send private message  
 
Display posts from previous:     
Jump to:  
All times are GMT + 1 Hour
Post new topic   Reply to topic
View previous topic Log in to check your private messages View next topic